Previously we had blown insulation on the outside wall only. This time we insulated with roll insulation which was quite a bit less messy. Just for good measure the entire room was insulated both for thermal properties and for noise-canceling properties.
Day 5: October 16th, 2009
Days 6,7,8: October 17th, 18th, and 19th, 2009
The next few days Ty stopped over to begin the process of mudding the drywall and making all those minor defects and gaps disappear. Ty didn't take very long either to mud all five walls and the ceiling. He did relate a fun fact to me however. Did you know that up until around 1980 drywall cement contained asbestos as an additive to keep it from shrinking? Apparently with asbestos added, drywall cement could be applied and it would dry exactly as applied in one day. Naturally, asbestos was removed as an
The magic of drywall cement and a skilled hand made several gaps and holes disappear. Unfortunately when the first team hung the drywall the completely missed one of the outlet boxes (I guess it was flush with the stud instead of standing out from it) so Ty had to do some exploratory cutting on the north (sink) wall to find it. And find it we did. A little more mudding and you could hardly tell there was ever a problem.
Days 9,10,11: October 20th, 21st, and 22nd
Once the drywall was done it was time to prime the inside of the bathroom and paint the ceiling so we wouldn't need to worry about dripping paint into the brand new tub and enclosure. Since priming isn't all that interesting I'll just skip to the tub installation.
Day 12: October 23rd
At last the fruits of our labor were about to pay off in something a bit more aesthetically pleasing than drywall (apologies to Ty) - a new tub and surround. For this job we hired Bath Fitter to break up and remove our old porcelain-covered cast iron tub and replace it with an acrylic tub and one-piece custom-fitted surround enclosure. The enclosure runs all the way to the ceiling. In addition, they were to frame the bathroom window on the west side wall, replace all the existing bath hardware, and install a new anti-scald valve in the plumbing behind the tub.
However, not everything went as smoothly as one would hope. In the process of installing the anti-scald valve a pipe was twisted and broken in the wall between the basement and the second floor. This resulting in two more people showing up to the house - a plumber and a Bath Fitter supervisor.
Somewhere in all this pipe fixing it was deemed necessary (without asking permission) to cut into my new subfloor in the bathroom. I cannot fathom why they needed to do this since there are only two pipes covered by the floor - the toilet drain and the sink drain - neither of which would be involved in fixing this breakage. If they were exploring under the floor I would have preferred a call or text from Dawn and I could tell them exactly what was under there. As such, I was left with a somewhat structurally unsound floor on the right side because they cut it in a way that the newly-unsecured piece was free to bob up and down as people walked across it.
When I got home I was left with a lovely new bath tub that worked, a lovely new surround and bath hardware, a cut up sub-floor, a broken valve handle, a hole in my downstairs wall, mysteriously low water pressure in the basement sink from the level it had been at in the morning, and no idea if Bath Fitter intended to pay for the repairs to my wall and/or stick me with the bill for the plumber. I called and left a message that night and am waiting to hear back from them. Hopefully we can sort this all out and I can still recommend them to others. At this point however, I would not recommend Bath Fitter if you have an older home with less than good condition pipes.
Days 13 and 14: October 24th and 25th, 2009
Dawn seems to be pleased with the new tub after she took a relaxing bath in it on Sunday. No more stupid shelf in the back of the tub keeping her from being able to lie down almost completely (it is a 5 ½' tub). Spooks our cat also appears to like the new tub because there more room to sit and walk around on the edges now.
Update: Bath Fitter returned my call and the supervisor who was at my house explained why the floor had been cut, apologized for the cold water valve and offered to at least provide me the replacement part (because I said I can do the replacement myself), and made some tentative offer to possibly split the cost of the plumber based on how much it cost. Normally plumbing-related costs due to poor existing infrastructure is on the homeowner, which I can understand. He also asked if we needed someone to come repair the marks in the wall. This makes me feel a little better about Bath Fitter though I would have rather not had to call and ask why things were damaged or broken.
Here are a few more pictures...